Plans for Re-Paving Summit & N. 4th Sts.

US23Paving Header

Very big changes are in the works for traffic flows on 2 main thoroughfares in the University District: Summit St. and N. 4th St.

Maps were presented at a community meeting on March 4th. Copies are available here.

The public comment period is open and scheduled to last until March 18th.   Feedback on this project may be sent:

via email to drortman@columbus.gov

or mailed to
attn.: Richard Ortman
50 w. Gay street
Columbus, ohio 43215

614-645-5465

The project includes:

  • Installation of a protected bike lane on Summit Street between
  • 11th Avenue and Hudson Street  – (columbus.gov/protectedbikelanes)
  • Relocation, removal and addition of some parking meters on Fourth and Third Streets
  • Relocation and removal addition of some parking spaces on Fourth and Summit Streets
  • Installation of queue box pavement markings – (columbus.gov/queuebox)
  • Restriping to provide bike lanes
  • Installation of bus bulbs (columbus.gov/protectedbikelanes)

Project Schedule:

Design began in spring 2014 and is scheduled for completion in spring 2015
Construction is tentatively scheduled to start in June 2015